Tiburon is rebuilding the two beaches at Blackie's Pasture without seawalls or riprap. The new shoreline along Greenwood Beach and Brunini Beach is made of sand, gravel, cobble and logs, placed so that waves can pull it out and push it back in. When the fencing comes down later this fall, the beach is supposed to keep changing shape. The town calls the approach a "living shoreline," and the changing shape is how it's meant to work.
What the contract pays for
The Tiburon Town Council voted 3-0 on Aug. 19 to give the construction contract to Livermore-based Goodfellow Bros. for $468,983. The vote also let the town manager approve change orders of up to 15%, which puts the ceiling at $539,330, according to The Ark. The Ark's report lists the work:
- Grading back the eroding scarp, the steep face where waves have cut the beach away
- Removing and disposing of asphalt
- Installing two rock sills at Brunini Beach
- Placing a log backstop at Greenwood Beach
The Marin Independent Journal describes the project as 1.4 acres along Richardson Bay. The work includes clearing debris, restoring beach, wetland and transitional habitat, and planting native vegetation. The Independent Journal also reports that the town will be fully reimbursed for the contract from a $1.5 million grant it received from the California State Coastal Conservancy in 2024. The Southern Marin Ledger gives the numbers differently. It says the council voted on Oct. 16, 2024, to tentatively accept a $1.4 million Coastal Conservancy grant, and that the full project is budgeted at $1.5 million in the town's adopted FY2026-27 Capital Improvement Program.
Why these two beaches were washing away
Most of the land along this stretch was never solid ground. A July 2025 project data report describes the site as a historic salt marsh that was filled and reclaimed, then used as a private horse pasture before it became Blackie's Pasture Park. The park takes its name from Blackie, a former Presidio cavalry horse who grazed the meadow for 28 years. Albert Guibara's bronze sculpture of him has stood at the site since 1995.
According to the same report, erosion and sand loss sped up around 2012. The beach was left mostly as a layer of coarse leftover material, and old fill, including asphalt, began washing into the bay. That explains why asphalt removal is on Goodfellow's list. Some of what crews are clearing is the old fill that the eroding beach has been exposing.
Many shorelines would get boulders at this point. The project page hosted by Audubon states one of the design goals directly: to head off the usual emergency response of placing riprap, which would make the beach loss more permanent and hurt the shoreline's scenic, recreational and habitat value.
How a beach is designed to move
The design relies on waves to spread the new material. David Eshoo, engineering manager for Tiburon's Public Works Department, described it to The Ark:
"We're installing a living shoreline, meaning that the material that's being installed here at this beach, the wave action will pull the material out and push it back in so that it doesn't erode any of the areas along Blackie's Pasture."
The Independent Journal adds detail, citing a 2024 Conservancy report. Coarse beach sediment is placed along the shoreline, and waves then redistribute it into a natural beach profile. Cobble salt-marsh drift sills are meant to hold sediment in place without stopping its natural movement. The Audubon page lists the rest of the design: regraded scarps held in place by native sand-trapping beach vegetation, large woody debris, and low drift sills running perpendicular to the shore.
The county has already been tracking how sand moves here. Before construction, the County of Marin placed fluorescent-dyed sand tracers at four spots on the site to follow sediment movement during storms, according to the Southern Marin Ledger. The town says the dye is environmentally safe.
All of this means the beach will look different from one season to the next. The Audubon project page includes a rendering of the design elements and the proposed site conditions about three years after construction.
A test the town plans to learn from
At the Aug. 19 meeting, Councilmember Alice Fredericks asked whether the approach was "considered superior to boulders and rocks." Eshoo answered, "Absolutely, that is correct," the Independent Journal reported. He also said the project will serve as a pilot that the town could repeat in other areas.
That pilot role ties in with a larger plan. Tiburon is separately writing a shoreline adaptation plan, funded by a grant of nearly $600,000 from the California Ocean Protection Council received in August 2025, with the planning process expected to finish by January 2028. The Southern Marin Ledger, citing the Independent Journal, quotes town climate official Grace Ledwith describing the goal as "a long-term road map, so to speak, that helps Tiburon make informed decisions about future investments." The results at Greenwood and Brunini beaches over the next few years will be some of the clearest local evidence for that plan.
Where the schedule stands
The schedule has been reported in more than one version, and the sources don't fully agree on the end date.
| Milestone | Date | Source |
|---|---|---|
| Drift sill built, first phase | March 23–26, 2026 | Town of Tiburon notice |
| Contract awarded to Goodfellow Bros. | Aug. 19, 2026 | The Ark |
| Town posts "Greenwood Beach Restoration Project Begins This Week" | Aug. 31, 2026 | Town of Tiburon notice |
| Planned fall start | Sept. 8, 2026 | The Ark |
| Completion forecast, four to six weeks | Around mid-October | Southern Marin Ledger |
| Completion forecast, construction | Nov. 20, 2026 | Marin Independent Journal |
The Southern Marin Ledger reports that construction has to happen outside the nesting and birding season set by the California Department of Fish and Wildlife. Finishing construction doesn't end the project, either. Eshoo told the Independent Journal that establishment periods, monitoring and maintenance will follow.
Walking Blackie's while the work is underway
The active beach work areas are closed during construction. Eshoo told the Independent Journal that "construction equipment and trucks" will travel through parts of Blackie's Pasture to reach the work area. He added that "the Town's intent is to maintain public access to as much of Blackie's Pasture and the surrounding trail system as practical, while restricting access to the active construction and staging areas."
The drift sill from March is already in place, and it comes with a specific request. The Audubon project page asks park users not to remove rocks or cobbles from the sill and not to walk on it, so the small plants installed there don't get trampled. Questions go to the Parks Maintenance Division at 415-435-7354.
The other project on the same stretch
Anyone driving out to Blackie's this fall will pass a second job. Caltrans is doing preventive maintenance on State Route 131, which runs from East Blithedale Avenue at Tower Drive to the downtown Tiburon roundabout near Main Street, as Caltrans spokesperson Matt O'Donnell explained to The Ark. Caltrans' Sept. 16 advisory said curb ramp and sidewalk work could begin as early as Monday, Sept. 21. Crews were to start near the US-101 interchange and work east toward the waterfront under intermittent one-way traffic control on weekdays from 7 a.m. to 5 p.m. The advisory also warned that pedestrian detours might be needed and that some bus stops might be affected.
Phase one includes 28 curb ramps, with paving scheduled for spring 2027. The Caltrans project page also describes bikeways from Tower Drive to Blackfield Drive, including a temporary two-way Class I bike path on the inbound side of the highway from Strawberry Drive to Blackfield Drive. The Ark has reported that bike lanes inside Tiburon were pushed to a later phase. Caltrans plans to pause over the winter. The Ark reported an expected finish of July 2027, while the Caltrans project page gives "winter of 2027."
The Caltrans work has an end date in 2027. The beach at Greenwood and Brunini is designed to keep being reshaped by wave action long after Goodfellow's trucks leave the park.
Projects like this are part of how the Richardson Bay waterfront is changing. If you'd like to talk about what the town's shoreline planning means for a home you own or are considering, Greg Corvi is glad to walk through it with you. Request a complimentary home valuation & consultation.